Tag No.: K0130

Facility facility failed to comply with hospital licensing rules (HLR) for pharmacy IV preparation room. Findings included the following:

Surveyor observed between 10 and 11 am on April 06, 2011 that hospital pharmacy IV preparation room ceiling and door swings were not in accordance with HLR 133.163(x)(2)details:
(A) Flooring in the IV solutions area for the preparation room, hood room and chemo-hood room shall be seamless and coved to the wall.
(B) IV solutions area ceiling and wall finishes for the preparation room, hood room and chemo-hood room shall be interlocking monolithic panels and sealed together or monolithic epoxy-painted gypsum board. The ceiling shall be coved to the wall.
(C) All penetrations in the walls and ceilings shall be sealed.
(D) The door from hood room shall swing into the preparation room. The door from preparation room shall swing into the chemo room. The door from preparation room shall swing into pharmacy.

Construction project shall be submitted to the department to provide this upgrade.

LIFE SAFETY CODE STANDARD

Tag No.: K0130

Facility facility failed to comply with hospital licensing rules (HLR) for pharmacy IV preparation room. Findings included the following:

Surveyor observed between 10 and 11 am on April 06, 2011 that hospital pharmacy IV preparation room ceiling and door swings were not in accordance with HLR 133.163(x)(2)details:
(A) Flooring in the IV solutions area for the preparation room, hood room and chemo-hood room shall be seamless and coved to the wall.
(B) IV solutions area ceiling and wall finishes for the preparation room, hood room and chemo-hood room shall be interlocking monolithic panels and sealed together or monolithic epoxy-painted gypsum board. The ceiling shall be coved to the wall.
(C) All penetrations in the walls and ceilings shall be sealed.
(D) The door from hood room shall swing into the preparation room. The door from preparation room shall swing into the chemo room. The door from preparation room shall swing into pharmacy.

Construction project shall be submitted to the department to provide this upgrade.