Bringing transparency to federal inspections
Tag No.: K0025
The facility did not ensure that smoke barriers were constructed to provide at least a one half hour fire resistance rating in accordance with 8.3 and as required by the LSC
On 04/05/16 at 10:30 AM and at times throughout the day, The surveyor along with the Facilities Director & Maintenance Supervisor observed that the smoke barrier walls above the suspended ceiling assembly for the corridor smoke doors, and the fluting of the corrugated decking and adjacent smoke barriers walls had voids and penetrations used for the passage of wires, conduit, etc. that were not sealed with materials having at least a half hour fire resistance rating as required.
Tag No.: K0025
The facility did not ensure that smoke barriers were constructed to provide at least a one half hour fire resistance rating in accordance with 8.3 and as required by the LSC
On 04/05/16 at 10:30 AM and at times throughout the day, The surveyor along with the Facilities Director & Maintenance Supervisor observed that the smoke barrier walls above the suspended ceiling assembly for the corridor smoke doors, and the fluting of the corrugated decking and adjacent smoke barriers walls had voids and penetrations used for the passage of wires, conduit, etc. that were not sealed with materials having at least a half hour fire resistance rating as required.