Tag No.: K0130
Based on observations, the facility failed to provide proper exhaust pressures in medical waste rooms. This deficient practice could affect patients, staff and visitors if proper ventilation of bio- hazardous air is not exhausted properly. Alternative life safety measures will be required throughout the monitoring of the facility corrections.
Findings Include:
1. Corrected 1/15/15
2. Due to the number, variety, and severity of the life safety deficiencies observed during the survey walk-through, the provider shall institute appropriate interim life safety measures until all cited deficiencies are corrected. The provider shall include, as an attachment to its Plan of Correction (PoC) and referenced therein, a detailed narrative and proposed schedule for all such measures. The narrative shall describe all measures to be implemented, as well as the frequency with which they are to be conducted, and shall indicate the manner in which the measures are to be documented. The narrative shall also include comments related to changes in the interim life safety measures to remain in place as work toward the completion of its PoC progresses.
Tag No.: K0145
Based on random observation during the survey walk through while accompanied by the facility electrical supervisor, the surveyor found that the electrical system installation did not meet all of the requirements of NFPA-70. This could affect all occupants of the hospital if the emergency power system does not operate correctly.
Findings include:
1. On 5/13/14, the surveyor observed that the transfer switches in the main electrical rooms were serving distribution panels that served a mixture of life safety panels and critical panels throughout the buildings. This does not meet the requirements of NFPA-70, Section 517-30 through 517-35, for a system that serves over 150 KVA in loads.
2. On 5/12/14, the surveyor observed that the panel EMLP in the boiler room, panel FP1 and the emergency distribution panel in the Building-C fire alarm room were serving a mix of life safety, critical and equipment loads. These are examples of, but not of the panels that do not meet the requirements of NFPA-70, Section 517-32 through 517-34.
3. On 5/13/14, the surveyor observed that the Life safety panel EM-3, and critical panel CR-S3-1, (new panels in a remodeled area of building D), are served from a single transfer switch. NFPA-70, Section 517-30 requires that each branch of the emergency power system be served from its' own transfer switch for emergency power systems with maximum demand over 150 KVA.