The information below comes from the statement of deficiencies compiled by health inspectors and provided to AHCJ by the Centers for Medicare and Medicaid Services. It does not include the steps the hospital plans to take to fix the problem, known as a plan of correction. For that information, you should contact the hospital, your state health department or CMS. Accessing the document may require you to file a Freedom of Information Request. Information on doing so is available here.
DANVILLE STATE HOSPITAL | 50 KIRKBRIDE DRIVE DANVILLE, PA 17821 | April 11, 2018 |
VIOLATION: Sprinkler System - Installation | Tag No: K0351 | |
Based on observation and interview, it was determined the facility failed to provide complete sprinkler coverage, affecting one of fifteen smoke compartments in this component. Findings include: 1. Observation on April 10, 2018, at 8:56 AM, revealed the unit 222 consumer telephone enclosures lacked sprinkler coverage. Exit interview with facility administrator, facility representative #1 and maintenance representative #1 on April 11, 2018, between 10:15 AM and 10:30 AM, confirmed the unit 222 phone enclosures obstructed the available sprinkler coverage. |
||
VIOLATION: Corridor - Doors | Tag No: K0363 | |
Based on observation and interview, it was determined the facility failed to maintain one of over 251 corridor doors in this component. Findings include: 1. Observation on April 10, 2018, at 9:16 AM, revealed the Unit 212 med room had a dutch door that lacked a required rabbet, bevel or astragal. Exit interview with facility administrator, facility representative #1 and maintenance representative #1 on April 11, 2018, between 10:15 AM and 10:30 AM, confirmed the gap between the upper and lower half of the unit 212 med room dutch door was not sealed. |
||
VIOLATION: Building Construction Type and Height | Tag No: K0161 | |
Based on observation and interview, it was determined the facility failed to maintain building construction requirements, affecting four of four floors in this component. Findings include: 1. Observation on April 10, 2018, between 8:15 AM and 1:45 PM, revealed the facility exceeds the maximum allowable story height for this type of construction. Exit interview with facility administrator, facility representative #1 and maintenance representative #1 on April 11, 2018, between 10:15 AM and 10:30 AM, confirmed the facility exceeds the maximum allowable story height for this type of construction. |
||
VIOLATION: Vertical Openings - Enclosure | Tag No: K0311 | |
Based on observation and interview, it was determined the facility failed to construct and maintain vertical enclosures, affecting four of four floors in this component. Findings include: 1. Observation on April 10, 2018, between 8:15 AM and 1:45 PM, revealed vertical enclosures to include exit stair towers, elevator shafts, dumbwaiter shafts and mechanical chases, did not have the required 2-hour fire resistance rating. Exit interview with facility administrator, facility representative #1 and maintenance representative #1 on April 11, 2018, between 10:15 AM and 10:30 AM, confirmed vertical enclosures did not have the required fire resistance rating. |